Wind park design in Kafireas, Euboea (nominal power 16,10 MW)
Routing – Transmission line final design
Underground cable design
Design of underground cable connection with underwater cable
Road construction design
Consulting services during the transmission line construction phase
Approval and building permit of the substation in Gratsiani 150/33 KV and connection design for the substation underground connection 150/ 33 KV with the grid
Approval and building permit of the substation in Gratsiani 150/ 33 KV
Topographic survey
Structural drawing
Landscape design
Excavation plan
Floor plan (basement, ground floor, rooftop)
Sections - Views
Structural stability design
Mechanical drawings and design
Connection design for the substation underground connection 150/ 33 KV with the grid
Substation in Gratsiani construction design 150/ 33 KV
Preparation of final design for the transmission line of the wind park 40 MW in position Makrinoros, municipality Nafpaktia, region Aetolia-Acarnania
Master data tables
Pylons chart
Topographic profile & topographic area plan
Arresters chart
Resistance grounding
Transmission line routing map and triangulation
Overhead transmission line crossing map
Cadastral surveys with the alleged owners
Cable arrangement and grounding conductor
Cable spacers setting and grounding
Towers cross section
Construction technical specifications
Construction Cost Budget
Final design study for the Extra High Voltage Center and interconnection grid (400 KV overhead transmission lines) for the project in the area of Amfilochia
Final Design for the Extra High Voltage Centers
400 KV Interconnection grid final design study
Cadastral surveys and plans compilation for the characterization of the 400 KV overhead transmission line
Cadastral surveys of the area surrounding the Extra High Voltage Center in Amfilochia and Achelou
Wind park design study services in the position Maggulios and Plagia - Psiloma, total nominal power 30 MW
Final design study for the 20/150 KV substation expansion in Skourta
Substation grounding and lightning protection design studies
High voltage design
Mechanical strength design
Medium – Low voltage design
Civil engineer design studies
Final design study for 150 KV single circuit transmission line, according to the specifications of IPTO that will connect to the existing substation couplers
Master data tables
Pylons chart
Topographic profile & topographic area plan
Arresters chart
Resistance grounding
Cable arrangement and grounding conductor
Cable spacers setting and grounding
Towers cross section
Final design study of the double circuit 150 KV overhead transmission line and forest road construction design study in the position Georgana Verias
Final design of interconnected transmission line
Master data tables
Pylons chart
Topographic profile & topographic area plan
Arresters chart
Resistance grounding
Cable arrangement and grounding conductor
Cable spacers setting and grounding
Towers cross section
Consulting
Consulting services during the construction phase
Forest road design study for the access to the pylons
Topographic area road plan C category (road for tractors)
Topographic profile road plan C category (road for tractors)
Forest road C category cross section plan (road for tractors)
Soil replacement plan
Health and safety planning and documentation
Technical report
Design study for the disconnection of the transmission lines in Koumoundourou - Megalopolis I and Koumoundourou - Megalopolis ΙΙ
Prerouting and final design study of the alternative disjoint of the double circuit 150 KV overhead transmission line according to the specifications of IPTO
Forest road design study for the access in the above transmission lines
Landscape restoration design study
Final design study for the connection of the 33/150 KV substation transmission line in Kasidiaris with the grid
Routing – Overhead transmission line final design
Master data tables
Pylons chart
Topographic profile and area plan
Arresters chart
Resistance grounding
Transmission line routing map
Cable arrangement and grounding conductor
Towers cross section
Design routing study for the overhead transmission line of the wind park in the position Kasidiaris I (Kranies – Karakaravamia – Elatos), area Lavdani municipality Pogoni, region Epirus, nominal power 50 ΜW
Consulting services and designs
Design services in the development of the electricity production Wind park in the position Lyrkio, municipality Mantinia and Lyrkio, region Arcadia , total nominal power 40 MW
Transmission line connection final design
Consulting services for the construction of transmission line
Design services for the production of an electricity power Wind park in the position Panio mountain, municipality Lavrotikis, region Attica, total nominal power 22,95 MW
Location scouting for the 20 KV/ 150KV substation
Topographic survey of 20 KV/ 150KV substation
Final interconnection design for transmission line
Consulting services for the construction of transmission line
Alternative interconnection design of the existing under dismantle section of the 150 KV overhead transmission line in the substation Gorofaki with the grid
Topographical profile on an alternative route interconnection Alternative interconnection topographical profile
Tower cross section
Phase sequence
Design services for the interconnection of the wind parks (Vagia and Kokkino in Boeotia, each total nominal power 40 MW)
Final design of the interconnection of each substation 20/ 150 V with the transmission line
Consulting services for the construction of transmission line
Electrical and mechanical designs of the substation 150/ 20KV 40/ 50MVA in the position Paleochori, municipality Mouzaki, region Karditsa
Single-line electric diagram
General layout of Electrical and Mechanical equipment/ Views
General layout of Electrical and Mechanical equipment/ Sections
General layout of Electrical and Mechanical equipment (Clamps list)
Lightning protection - General arrangement
Electrical and mechanical designs of the substation 150/ 33KV 65/75MVA in the position Siatista, municipality Voio, region Kozani
Single-line electric diagram
General layout of Electrical and Mechanical equipment/ Views
General layout of Electrical and Mechanical equipment/ Sections
General layout of Electrical and Mechanical equipment (Clamps list)
Lightning protection - General arrangement
Design services for the construction of the wind park in the position Kerdos – Chodri rachi, municipality Mantoudi – Limni – Agia Anna, region Euboea, nominal power 39,95 MW
Location scouting for the 20 KV/ 150KV substation
Topographic survey of substation 20 KV/ 150 KV
Final interconnection transmission line design
Consulting services for the construction of the transmission line
Design for the construction of wind park in the position Cithaeron in the regions Attica and Boeotia
Design study of the exact position for the 30 wind turbine generators on the ground in stake out
Topographic survey of the area between pylons 6 and 7 of the high voltage transmission line
Road construction design study
Connection design of 150 KV substation of enrichment factory in Skouries with the 150 KV grid of IPTO
Routing – 150 KV Transmission line final design
Forest road construction design
Design preparation for the connection of substation 20/ 150 KV in Skouries to HETS
Substation design 20/ 150 KV Skouries
150 KV transmission line design of approximately 3km length
Forest road planning and landscape restoration
Connection final design of 150 KV power transmission lines with the 150/20 KV substations with the National interconnected electrical power transmission system
Substation 20/ 150 KV Ypato
Substation 20/ 150 KV Christianoupoli
Substation 20/ 150 KV Charaindini Thiva
Substation 20/ 150 KV Heraia
Substation 20/ 150 KV Kourtesi
Substation 20/ 150 KV Likofolia
Substation 20/ 150 KV Meligala
Preliminary design study for the overhead 110KV transmission line in Rostov, Russia
Evaluation of the route for the proposed 110 KV High Voltage transmission line to identify possible obstacles with preexisting structures and natural obstacles
Alternative route presentation, pylon positions and description of deviations of proposed route based on current legislation
Additional studies for the interconnection 150KV transmission lines of the wind parks in Kafirea
New pylon 1, 3, 4 site study in Amygdaleas transmission line
New phase sequence A, B, C study for the intersection after the temporary shutdown of the substation in Andia
New phase sequence A, B, C study and connection study with the underground cable in the Platanistou terminal
Category
High Voltage Power Lines & Electrical Substations Design